County Government
Leavenworth County
Leavenworth, Kansas
Project Scope
- Upgrade all lighting at County Justice Center
- Obtain over $80,000 in utility incentives
- Replace over 1,000 fluorescent troffers with new LED panels
- Upgrade 250 recessed can fixtures to LED downlights
- Install 250 LED retrofit kits
- Incorporate over 100 Emergency battery backups to new fixtures
- Installed by County staff overseen by ROI Energy to reduce costs
Financial highlights
Payback and customer-cost figures shown here exclude any installation credit reflected in internal project materials.
Total project cost
$286,941
Utility incentives
$108,614
Adjusted customer cost
$178,327
Annual electric savings
$36,734
Adjusted simple payback
4.9 years